Client: Agip Kazakhstan North Caspian Operating Company N.V. (Agip KCO)
General Contractor: Consortium Bonatti S.p.A – JS Company “Montazhspetsstroy” (MSS portion - 50%)
Construction area: Eskene West, Atyrau oblast, Republic of Kazakhstan
Construction period: 2007 – 2011
DETAILED SCOPE OF WORK includes, but is not limited to:
Procurement of materials, including:
Supply of materials for civil work, passive fire protection, painting, hot/cold insulation, required consumables.
ConstructionandInstallation, including:
Total number of man-hours completed under the Contract – more than 7,500,000 man-hours.