Contract for maintenance activities for the period of preventive overhaul during shutdown of Processing Plant at Chinarevskoye Oil and Gas Condensate Field; construction and installation works of H-501 Heater piping at the existing Processing Plant at Chinarevskoye Oil and Gas Condensate Field
Client: Zhaikmunai LLP
Contractor: JS Company “Montazhspetsstroy”
Construction area: West Kazakhstan oblast, Zelenovskiy district, Chinarevskoye field
Construction period: August, 2012 to October, 2012
Scope of Work included fabrication of spools and repair of 26 Work Packs, including: welding, heat treatment, NDE of welds, installation of supports, replacement of seals, painting, vessel cleaning, replacement of process unit trays, but not limited to earthwork, concrete work, fabrication and erection of steel structures, spools prefabrication and installation of pipelines, including pipe fittings, NDE of welds, pipeline testing, painting, heat insulation.
Total number of man-hours liquidated under the Project – 25,531 man-hours