Client: Agip Kazakhstan North Caspian Operating Company N.V. (Agip KCO)
General Contractor: JS Company “Montazhspetsstroy”
Construction area: Eskene West, Atyrau oblast, Republic of Kazakhstan
Construction period: 2004 – 2010
Scope of Work includes detailed design, procurement of materials and installation of tanks
DETAILED SCOPE OF WORK includes, but not is limited to:
Detailed engineering as per API-650 standard:
- detailed engineering calculations;
- development of detailed drawings and documentation – in total more than 6 000 documents;
Procurement:
- supply of all equipment and materials required for construction;
- material control;
- transportation to the Facility;
- unloading and storage of equipment and materials
Construction and Installation of 24 off tanks, including pre-commissioning (list of tanks is given below)
Project physical quantities completed:
- earthwork (excavation and backfilling) – 117,430 m3;
- concrete work (foundation construction) – 5,530 m3;
- erection of tank steel structures – 7,802 tonnes;
- painting – 83,500 m2;
- insulation – 30,500 m2;
- installation of tank mechanical equipment – 26 units;
- installation of instrumentation equipment – 186 units;
- installation of instruments cable – 12,100 m;
- installation of electrical cable – 64,500 m;
- installation of electrical equipment – 18 units;
- number of the prepared As-built documents under the Contract (Mechanical Completion Dossier, Quality Dossier, RoK Regulations Dossier, General Dossier, Pre-commissioning Dossier, MRBs and TOMMs, etc.) – 507 documents
Total number of man-hours completed under the Contract – 5 600 000 man-hours